30 Large Diameter 80 Ton Helical Piles Installed to Support Con Edison of New York Substation F at Brooklyn Navy Yard Next to Famous Steiner Studios

Scobbo Foundation Systems

Long Island, NY        Piscataway, NJ

(516) 944-7154        (516) 944-PIER

www.nynjhelix.com

IDEAL Group helical piles being unloaded at job site adjacent to the famous Steiner Studios complex.

Con Edison Substation F platform site preparation.


One 80 ton ultimate capacity compression load test was successfully completed.  The 30 helical piles were installed in 3 days.

8.625” diameter helical piles in 20 ft. sections being installed to an average depth of 40 ft.

Project Overview

Scobbo Foundation Systems was contracted to install 30 new construction helical piles to support the new Con Edison Substation F located in the Brooklyn Navy Yard adjacent to the well known Steiner Studios.  Caissons, drilled piers and H piles were considered, but due to close proximity to existing structures, vibration concerns were a significant factor.  For this reason and for overall project cost concerns, helical piles were selected.