Project Overview
There were several challenges on the project including very limited access for moving and positioning equipment. This was one of the primary reasons helical piles were selected for the project over timber piles - not to mention the vibration concerns associated with timber pile installation. Obviously water control presented a challenge, but the crew successfully completed the project in just (3) days.
Breslin Contracting Installs (30) Transition Helical Piles to Support a Covered Restaurant Deck on the Chesapeake Bay in Oxford, MD
Summer, 2024
Additional Information
- Helical Pile Leads: CHANCE SS5 to RS2875.203 5 transition piles with 6-10-12 inch helix bearing plates
- Extensions: SS5 to RS2875 casting transitions connecting to extensions
- Installation Depth: Average of 35 ft. with installation torque of 3200 ft. lbs.
- Pile Caps: Bolted new construction caps for uplift
- Installation Equipment: CAT 305 with a 16K Digga drive head & CTS TorqHub monitoring
- General Contractor: Ewing Construction
- Pile Design: Earth Anchoring Suppliers